Scope of Work
The Major scope of the work involves Civil and Structural including Precast I-Girders, Box Girders, Portal Beams, Parapets etc.
PCC - 1,512.699 cum
RCC - 20,362.304 cum
RCC - Precast Prestressed Works - 6,929.997 Cum
R/F Steel - 4,013.004 MT
Structural Steel - 407.578 MT
Post Tensionsing - 344.493 MT
FRP Roofing Sheet - 5,201.199 sqm
Erection of Precast Prestressed Box Girder for Segmental Construction - 25,345.166 MT
Erection of Precast Prestressed I-Girder - 2,068.459 MT
Erection of Precast Parapet - 9,043.923 MT
Erection of Cable Trough - 117.382 MT
2.529 KM of Viaduct works such as Foundation, Sub Structure, Super structure and including finishing works